Short answer: Construction on a typical kitchen remodel takes 4 to 8 weeks once demolition starts. That is the range we publish for our own kitchen projects. The full timeline is longer, because design, selections, ordering and permits all happen before anyone touches a wall. A cabinet-and-countertop replacement in the same footprint sits at the short end. A kitchen where walls come down, the sink moves to an island or the panel gets upgraded sits at the long end.
This guide walks through each phase in order, then breaks construction down week by week. It also flags the things that most often stretch a schedule in Fairfax County and the rest of Northern Virginia, so you can plan around them.

The big picture: four phases
Every kitchen remodel moves through the same four phases. Only the last one involves a crew in your house.
| Phase | What happens | What controls the length |
|---|---|---|
| 1. Design | Measure, layout, drawings, scope, contract | How many layout options you explore, and how quickly you decide |
| 2. Selections and ordering | Cabinets, countertops, tile, fixtures, appliances chosen and ordered | Product lead times, especially cabinets |
| 3. Permits | Building and trade permits filed and approved, if the scope needs them | Scope, jurisdiction and whether corrections are requested |
| 4. Construction | Demolition through final walkthrough | Scope, inspections, countertop fabrication |
Phases 2 and 3 usually overlap. Your contractor can file permits while cabinets are being built. The goal is for materials and permits to both be ready on the same day, so demolition doesn’t start until there’s nothing left to wait for.
Phase 1: Design
Design starts with a site visit. Someone measures the room, notes where the plumbing, gas, ductwork and electrical panel are, and checks for things that affect the layout: a soffit over the cabinets, a window that sits low, a bearing wall, a floor that isn’t level.
From there, the designer draws a layout, you react to it, and it gets revised. Expect to talk through:
- Whether the sink, range and refrigerator stay where they are or move
- Whether any walls come down
- Cabinet layout, including where the trash pull-out, pantry and drawer stacks go
- Lighting plan: recessed, under-cabinet, pendants
- Appliance sizes, since they set cabinet dimensions
The single biggest factor in how long design takes is decisions. A homeowner who knows they want the same footprint with new everything can move fast. A homeowner choosing between keeping the dining room wall or taking it out needs more time, and should take it. Changes are cheap on paper and expensive after demolition.
At City Kitchen & Bath, design is included, and the first design consultation is free. You can see our process from first meeting to handoff.
Related: Kitchen Remodel Checklist for Fairfax County Homeowners · Living Through a Kitchen Remodel: Temporary Kitchen Tips · Kitchen Remodeling in Northern Virginia: Complete Guide
Phase 2: Selections and ordering
Once the layout is set, you choose the products. This is where the calendar gets set, because some items take weeks to arrive.
Cabinets set the schedule
Cabinets almost always have the longest lead time in a kitchen. Stock lines can be quick. Semi-custom and custom lines are built to order. Painted finishes, special sizes and modified boxes can add time. You can compare cabinet lines in our showroom and ask about current lead times for each.
Countertops wait for cabinets
Stone and quartz countertops are templated after the base cabinets are installed, not before. The fabricator measures the real cabinets, then cuts the slabs. That gap is built into every kitchen schedule, and it is one of the main reasons kitchens take longer than bathrooms. You can still pick your slab or color early. Browse countertop options before design is final so the material is reserved.
Everything else
Tile, sink, faucet, hardware, lighting and appliances need to be chosen before construction starts, even if they are installed in week 4 or 5. Here’s why:
- Appliance specs set cabinet openings and electrical needs
- The sink model sets the countertop cutout
- The faucet sets the number of holes drilled in the stone
- Light fixtures set box locations during rough-in
A late decision on any one of these can stop work. Have everything on site, or confirmed in a warehouse, before demolition.
Phase 3: Permits in Fairfax County
Not every kitchen needs a permit. Fairfax County Land Development Services lists kitchen cabinets and countertops, tile and flooring replacement, and like-for-like replacement of electrical, plumbing and mechanical items in the same location as work that does not need a permit (When is a Permit Required).
The same page says permits are needed for interior alterations, which “includes kitchen renovations,” for new or relocated plumbing, gas and electrical fixtures, and for installing or removing walls, including non-load-bearing ones. Most full kitchen remodels hit at least one of those.
On timing, the County announced on April 30, 2026 that residential Fast Track plan review dropped from five business days to one for eligible projects. “Minor interior alterations” are on the eligible list. The County says eligibility depends on scope and complexity, so a project that removes a load-bearing wall may take longer. Trade permits (electrical, plumbing, mechanical) are pulled after the building permit is issued, according to the County’s residential addition and alteration permit page.
If you live in the City of Fairfax, the Town of Vienna or the Town of Herndon, the process is different. The City and Herndon handle their own permits, and Vienna requires Town approval first. We handle permits on our projects and will tell you which office applies to your address.
Phase 4: Construction, week by week
Here is how a typical kitchen construction schedule unfolds. This example assumes a full remodel: new cabinets and countertops, new flooring, some plumbing and electrical changes, and no structural work. A simple same-footprint swap moves faster. Structural changes add time, mostly at the start.
Week 1: Protection and demolition
- Floors outside the kitchen are covered and a dust barrier goes up
- Appliances are disconnected and removed
- Cabinets, countertops, backsplash and, if planned, flooring and drywall come out
- Hidden conditions show up: old water damage, undersized wiring, a duct in the wall you wanted gone
Demolition itself is often fast. The rest of week 1 is about what demolition reveals. Your project manager should walk you through anything unexpected and how it affects scope.
A note on older homes: Many Northern Virginia houses were built before 1978. Under the EPA’s Renovation, Repair and Painting (RRP) rule, firms paid to disturb paint in pre-1978 homes must be certified and follow lead-safe work practices. That adds setup and cleanup steps but not usually much calendar time.
Week 2: Rough-in
This is when the hidden work happens:
- Plumbing lines are moved or extended for a new sink location, dishwasher, ice maker or pot filler
- Gas line is run or moved for a gas range
- New circuits are pulled for appliances, outlets and lighting
- Ductwork is routed for a vented range hood
- Framing changes are made: blocking for wall cabinets, a new header, a soffit removed or rebuilt
If the project has a permit, rough-in inspections come next. Plumbing, electrical and framing must be inspected before walls are closed. Inspection scheduling can add a few days, and a failed item means a fix and a re-inspection.
Week 3: Drywall, then floors
- Insulation, where walls were opened to the exterior
- Drywall hung, taped and finished, which takes several days with drying time between coats
- Primer, and sometimes the first coat of paint, while walls are bare
- New flooring, if it runs under the cabinets
Whether flooring goes in before or after cabinets depends on the material and the plan. Tile and many hardwood installs go in first. Some floating floors go in after. Your contractor should explain the choice for your kitchen.
Week 4: Cabinet installation
Cabinets go in base first, leveled and shimmed, then wall cabinets. Fillers, panels, crown and light rail follow. Older houses here often have floors and walls that aren’t flat or square, and good installers spend real time correcting for it. That work is what makes doors line up and countertops sit flat.
Once the base cabinets are set and secured, the countertop fabricator comes to template.
Weeks 5 and 6: Countertop fabrication gap
This is the gap that surprises people. After templating, the fabricator cuts and finishes the slabs off site. While you wait, the crew keeps working:
- Remaining electrical trim-out that doesn’t depend on the countertop
- Under-cabinet lighting wiring
- Paint touch-ups
- Hardware installation
- Appliance placement where possible
Week 6 or 7: Countertops, backsplash and final connections
- Countertops are installed and sink is mounted
- Faucet, disposal and dishwasher are connected
- Range or cooktop is connected and tested
- Backsplash tile is set and grouted, usually after countertops so tile sits on the finished surface
- Final electrical trim: outlets, switches, fixtures, pendants
Final week: Inspections, punch list and walkthrough
- Final inspections, if permitted
- Punch list: anything chipped, misaligned or unfinished gets listed and fixed
- Cleaning
- Final walkthrough with your project manager, who should show you how to care for the new surfaces and appliances
A full remodel lands at 6 to 8 weeks of construction. A same-footprint project with no wall or plumbing changes can land closer to 4.
What stretches a kitchen remodel timeline
Most delays come from a short list of causes. Knowing them helps you ask the right questions up front.
| Cause | How it adds time | How to avoid it |
|---|---|---|
| Late selections | Work stops while a product is chosen and shipped | Choose and order everything before demolition |
| Backordered items | A single missing appliance or sink can hold up countertops | Confirm stock before the start date |
| Hidden conditions | Rot, old wiring or a duct in the wrong wall | Budget time and money for surprises in older homes |
| Change orders | New work after demolition needs new materials and sometimes new permits | Make layout decisions during design |
| Failed inspections | A fix plus a re-inspection | Use a licensed contractor who pulls permits as the responsible party |
| Structural changes | Engineering, beam ordering and framing inspection | Plan wall removal early in design |
One cause people underestimate is the number of separate trades. Plumbers, electricians, drywall, flooring, cabinet installers, fabricators and tile setters all need to show up in order. When a contractor relies on outside crews, one no-show can push the next trade. We use in-house installers rather than subcontracted crews, and every project has a dedicated project manager who owns the schedule. For more on sequencing, see our post on how trades are coordinated during a kitchen remodel.
How a kitchen compares to a bathroom
People often plan both. On our projects, bathrooms typically take 2 to 4 weeks of construction and kitchens 4 to 8. The kitchen takes longer because of the cabinet volume, the countertop templating gap and the number of appliance connections. If you are doing both, talk with your designer about whether to run them back to back or at the same time. Doing them together shortens the total disruption but means two rooms out of service at once.
Local timing notes for Northern Virginia
- Older homes, more surprises. Many colonials, split-levels and ramblers in Fairfax County were built in the 1960s through 1980s. Original wiring, galvanized supply lines and ductwork in kitchen walls are common finds. Leave room in the schedule.
- Jurisdiction matters. A house in Burke, Springfield, Annandale or Oakton files with Fairfax County. A house inside the City of Fairfax files with the City. Vienna adds a Town step. Your contractor should know which applies before quoting a start date.
- Holidays. Many homeowners want the kitchen done before Thanksgiving or a December gathering. Work backward from the date you need it, and add the full design and ordering window, not just construction.
Frequently asked questions
How long does a kitchen remodel take from start to finish?
Construction typically takes 4 to 8 weeks. Before that, design, selections, cabinet ordering and permits happen, and that work often takes longer than construction itself. The total depends mostly on cabinet lead times and how quickly decisions are made.
What is the longest part of a kitchen remodel timeline?
Usually the wait for cabinets, which happens before construction starts. During construction, the gap between countertop templating and installation is the longest single wait.
Can I use my kitchen during the remodel?
Not for most of it. From demolition until the sink and appliances are reconnected, the kitchen is out of service. Plan a temporary kitchen elsewhere in the house for the whole construction period.
Does a permit add time to a kitchen remodel in Fairfax County?
It can. Review happens before construction, and inspections happen during it. As of April 30, 2026, Fairfax County reported one-business-day Fast Track review for eligible residential projects, including minor interior alterations. Larger or structural projects may take longer.
Why can’t countertops be ordered before the cabinets are installed?
Stone and quartz fabricators template from the installed base cabinets so the finished tops fit the real room, which is rarely perfectly square. You can choose and reserve your material early, but cutting waits for the template.
How can I keep my kitchen remodel on schedule?
Make all layout and product decisions during design, confirm every item is in stock before demolition, and avoid changes after work starts. Hire a licensed contractor with a dedicated project manager who coordinates every trade and inspection.
Plan your kitchen remodel timeline with us
We’ll map your schedule at the design stage, including lead times, permits and construction weeks, before you commit to a start date. Learn more about our kitchen remodeling work, visit our showroom at 3204 Old Pickett Rd, Fairfax, VA 22031, call (703) 552-5252, or book a free design consultation. Showroom hours are Monday through Friday, 9:00 a.m. to 5:00 p.m., and Saturday, 10:00 a.m. to 4:00 p.m.